Step-by-Step Process

When you log in to eResearch Proposal Management (eRPM), your Home workspace displays. Note the following:

  • The Inbox tab shows deliverables that are due now or past due.
  • The Upcoming tab shows deliverables with upcoming due dates.
  • The Completed tab shows completed deliverables, completed date, and who they were completed by.
  1. Verify the Innovation Partnerships - Compliance role is selected.
  2. Click on the Award link.
  3. Click the Innovation Partnerships Compliance Manage Deliverables activity from the Award workspace.

See the steps below to Complete or Remove a deliverable.

Complete a deliverable:

  1. Click Complete.
    Note Only complete deliverables that have a Responsible Party of "Innovation Partnerships-Compliance".
  2. Click Add or drag and drop file(s) to attach completed documents.
    Warning Do not upload any export controlled information or data.
  3. Enter Completion Comments which will display on the Deliverables tab of the Award workspace.
  4. Enter the Date submitted to the sponsor.
  5. Enter or select who submitted to the sponsor.
  6. Click OK on the dialog box.
  7. Click OK to save.

Notes

  • The Status on the Deliverables tab will show Completed, and the activity will be recorded on the Activity Log on the Award workspace.
  • Completed Deliverables will move to the Completed tab on your Home workspace.

Remove a deliverable:

If you or someone else accidentally created an Innovation Partnerships-Compliance deliverable, then you can delete it.

  1. Click Delete next to the deliverable you want to remove.
    Note Only delete deliverables that have a Responsible Party of "Innovation Partnerships-Compliance".
  2. Click OK on the dialog box.
  3. Click OK to save.

Note The Deliverable will be removed from the Deliverables tab on the Award workspace.